On 25 April 2017, the operator responsibilities for the Asse II mine as well as the Konrad and Morsleben repositories were transferred to the Federal Company for Radioactive Waste Disposal (Bundesgesellschaft für Endlagerung mbH, BGE). This website of the Federal Office for Radiation Protection (BfS) will therefore no longer be updated and displays the status as on 24 April 2017. You will find current information at the BGE: www.bge.de

Navigation and service

Documents relating to the plan-approval procedure

The documents relating to public participation were submitted to the plan-approval authority, the Ministry of Agriculture and Environment of Saxony-Anhalt (MLU), on 13 September 2005.

The essential challenge to the project also becomes clear by the fact that the licensing authority (MLU) took about four years to declare that the documents were suitable for being laid out to public inspection. On account of the large complexity of the project the MLU had already considered detailed documents that would actually have to be examined in detail later on and not already in the process of declaring that the documents were suitable for being published in the public participation procedure.

Following comprehensive technical discussions of this topic and many comments by experts, part of which also referred to detailed documents that would actually have to be examined later on, the Federal Office for Radiation Protection (BfS) entirely revised the documents required for public inspection according to the requirements of the MLU and submitted them again in January 2009. The licensing authority terminated the examination of the documents in September 2009 and declared that they be suitable for the public participation procedure.

The MLU displayed the documents required for public participation in Magdeburg, Erxleben and Helmstedt in the period from 22 October until 21 December 2009. Furthermore the BfS has published the documents on its homepage, which continues to be accessible for all interested persons.

Apart from the documents for public participation the BfS has prepared a multitude of documents describing in detail the individual decommissioning measures and containing the analyses that are necessary to assess the long-term safety. The MLU is now in possession of ca. 200 documents for examination. Currently detailed planning is being carried out relating to the individual project measures which take into account the already available examination results of the MLU.

Access to relevant and other documents

The main statements from the relevant procedural documentation were summarised in the document "Decommissioning of ERA Morsleben - Plan for the decommissioning the repository for radioactive waste" (in German only). The complete documents relating to the plan-approval procedure are also only available in German language and can be found on the German homepage.

State of 2015.05.28

Transfer of operator responsibilities

On 25 April 2017, the operator responsibilities for the Asse II mine as well as the Konrad and Morsleben repositories were transferred to the Federal Company for Radioactive Waste Disposal (Bundesgesellschaft für Endlagerung mbH, BGE). Previously, the responsibility for the projects was with the Federal Office for Radiation Protection (BfS). The foundations for the change of operatorship are laid down in the "Act on the Realignment of the Organisational Structures in the Field of Radioactive Waste Disposal", which became effective on 30 July 2016. The BfS focusses on the federal tasks of radiation protection, for example in the field of defence against nuclear hazards, medical research, mobile communication, UV protection or the measuring networks for environmental radioactivity.

© Bundesamt für Strahlenschutz