The drilling device is set up in the work area in front of emplacement chamber 7
Transport of the drilling device to the work area
With extreme care Asse staff took the drilling device to its future operational site in front of emplacement chamber 7.
A Diesel driven forklift initially transported the drilling device into the steep inclining emplacement chamber 5. Then the device was lifted by a smaller forklift with electric drive and taken via the lock to its future operational site.
The drilling device is set down in the work area in front of emplacement chamber 7
Once the tent construction separating the radiation protection area from the residual mine has been completed, the interior fittings of the work area will be carried out in the weeks to come and the measurement containers will be equipped.